Arrangements of glass layout / measure date / installation date

Confirm glass frame condition / wall & pillar condition
*Comparison between drawing data and measure data, confirm other items.
Practice of JIS standard product inspection
Confirm scaffolding safe
1 : Safe confirmation of working spot
2 : Cleaning glass foundation
3 : Set setting-block
4 : Build up the first glass

5 : Glass adjustment / size confirmation

6 :Temporarily fix it (with wedges)

7 : Install from the second glass (adjust seam )

8 : Total confirmation (once after one span)
Fix with special bulking agent

1 : Hardening of bulking agent confirmation
2 : Unfasten wedges (after 1 done)
3 : Maintenance of connecting corners
1 : Cleaning the installation place (remove glass, and other foreign things)
2 : insert backup materials
3 : tape masking tapes
4 : insert sealant
5 : give a finish
6 : take off masking tapes
Clean after installation